Construction company, IERHA settle out of court, both silent on details
By Austin Grabish, The Selkirk Record
A construction company
that was originally awarded the tender for a new hospital in Selkirk filed a
lawsuit against the Interlake-Eastern Regional Health Authority after it was
dumped from the development less than a month after being named the lowest bidder
for the project in 2013.
And new documents obtained
by the Selkirk Record suggest the
reason the tender was cancelled was not because of an expansion to the project
as has been repeatedly reported by the RHA.
A 2013 statement of claim
filed by PCL Constructors against the Interlake-Eastern RHA alleges the
original tender was cancelled because of a complaint made by an unsuccessful
bidder on the project.
The tender in question
dates back to February 2013 when PCL submitted its bid for the project.
PCL was named the lowest
bidder after coming in $40,856 less than other bids on the multimillion-dollar
project, court documents say.
But on April 12, 2013,
less than a month after it was named the successful bidder, the RHA advised PCL
it was cancelling the tender.
The RHA said “an
opportunity for significant and efficient change to the project” had come to
its attention, and it would later publicly say the original tender did not
include plans for an MRI lab.
But PCL disputed the RHA’s
claim in court documents, alleging representatives at Manitoba Health informed
the company at an April 23 meeting the reason the tender was quashed was
because of a complaint made by an unsuccessful bidder.
A letter that was obtained
by the Record through a
freedom-of-information (FIPPA) request shows in May, the RHA contacted PCL
again, this time claiming the tender was being cancelled because of flaws in
the RHA’s tender documents.
Former Interlake-Eastern
RHA CEO John Stinson told PCL the RHA determined its original bidding documents
contained flaws that did not permit it to evaluate all bids fairly.
“Further, I acknowledge
that my correspondence of April 12, 2013 did not disclose all of the issues
surrounding Interlake-Eastern RHA’s decision to cancel the tender,” Stinson
wrote in the letter dated May 3, 2013.
PCL then asked the RHA to
see the flaws but the request was refused, court documents allege.
A request made by the Record to obtain the alleged flaws was
also denied by the RHA.
“The Interlake-Eastern RHA
has not received any other written complaints from bidders on this project and
therefore, these records do not exist,” a letter said.
The construction company went
on to sue the Health Authority for undisclosed damages, alleging the RHA caused
a loss of profit for the company.
It also alleged the RHA
breached an obligation by cancelling the tender on false and misleading
grounds.
It said the RHA utilized
the tender process to conduct a reverse auction and engage in a bid-shopping
process by obtaining information from all bidders and then re-tendering without
a valid cause.
The new hospital is
reported to be one of the biggest health capital projects in the province. It
has a construction budget of $111 million alone, and with equipment and
furnishings the final budget is estimated to be $159 million.
The legal spat between PCL
the RHA ended just five months after the lawsuit was filed.
No statement of defence
from the RHA was ever given to the court, and no details about any kind of a
potential settlement between the two parties have ever been made public.
Emails obtained by the Record show the Deputy Minister of
Health’s office was aware of the legal spat, as were other senior officials
with Manitoba Health.
In one email obtained
through a FIPPA request, Norman Blackie, executive director of capital planning
for Manitoba Health, calls the litigation surrounding the hospital “the ugly
file”.
Documents show three
companies had bid on the original tender. They were: PCL Constructors, Bird
Construction Company, and Graham Construction and Engineering.
The province announced
last spring the EllisDon Corporation had been awarded the construction tender
for the project, and work on the hospital began shortly after the announcement.
Both parties cited a
non-disclosure agreement between PCL and the RHA, as well as the Elections
Financing Act, which prevents the province and its agencies from publishing or
advertising information about its programs or activities in the days leading up
to an election.
A byelection is taking
place in The Pas on April 21.
A spokesman for PCL said
the company would not be providing comment as the dispute has been settled.
-- First published in the Selkirk Record print edition April 2 2015 p.2
At Naveen Hospital at Coimbatore provides personalized friendly care for mental health. With certified and experienced Psychiatrist, our services are extended to all age groups. Our Psychiatrist doctors promote better mental health with complete psychological treatment and we aim to treat comparatively earlier. We also provide prevention services for early identification and reduce the risk over the mental health. Our other services includes De-addiction, Rehabilitation center along with the Psychiatric services for mental health at Coimbatore, Tamil nadu.
ReplyDeleteMental hospital in coimbatore
Psychiatrist in coimbatore
Rehabilitation center for mentally ill